1897 New York hydropower plant diverted power to Bitcoin mining

  • The 5,250 kW Mechanicville plant on the Hudson River dates back to 1897
  • Operator Albany Engineering allocated part of its output to BTC mining in 2021
  • CEO Jim Besha Sr. said mining earned about three times more than grid sales
  • Mining was halted in 2022 as power prices made it unprofitable
Why it matters: The case shows mining competes directly with grid sales and hinges on power prices, not just the Bitcoin price.