HIVE pours over $250M into Paraguay data centers near the Itaipú Dam

  • —Paraguay data center investment topped $250 million over 18 months
  • —Current capacity is 300 MW, producing about 8.5 BTC per day
  • —Yguazú site targeted to reach 400 MW by Q3 2026
  • —Total commitments exceed $400 million; over 300 jobs created
Why it matters: Paraguay is becoming HIVE's core operation, and hitting 400 MW on schedule is key to its 35 EH/s hashrate target by end-2026.